A. INTRODUCTION

B. CHAPTER-SPECIFIC ROLES AND RESPONSIBILITIES

1. Building Manager
2. Safety Coordinator
3. Office of Facilities Management and Reliability (OFMR)
4. Office of Protection Services (OPS)
5. Smithsonian Business Ventures, FONZ, and other SI Business Operations

C. PROGRAM COMPONENTS

1. Training
2. Impairments
3. Required Inspections

D. RECORDS AND REPORTS

1. Original Records
2. ITM Documentation
3. Information Management System
4. ITM Report

E. REFERENCES

Attachment 1 - Automatic Sprinkler System
Attachment 2 - Standpipe and Hose Systems
Attachment 3 - Private Mains Used for Fire Service
Attachment 4 - Fire Pumps
Attachment 5 - Water Storage Tanks Used for Fire Protection
Attachment 6 - Valves and Fire Department Connections
Attachment 7 - Kitchen Ventilation Hoods and Fire Suppression Systems
Attachment 8 - Halon Systems
Attachment 9 - Clean Agent Fire Extinguishing Systems
Attachment 10 - Fire Detetion and Alarm Systems
Attachment 11 - Emergency Generator and Emergency Lighting
Attachment 12 - Fire Doors and Emergency Exists
Attachment 13 - Life Safety and Fire Fighters Service on Elevators
Attachment 14 - HVAC and Smoke Management Systems
Attachment 15 - Portable Fire Extinguishers
Attachment 16 - Lighting Protection Systems
Attachment 17 - Paint Spray Booths
Attachment 18 - NICET Certification


CHAPTER 35 - FIRE SYSTEMS INSPECTION, TESTING AND MAINTENANCE (ITM)

 

A. INTRODUCTION

1. This Chapter establishes the Smithsonian Institution (SI) requirements for performing inspections, operational tests, and preventive maintenance on all fire suppression, detection and alarm systems, smoke control systems, emergency and exit lighting, fire and exit doors, and all other fire protection and life safety systems or equipment.

2. The SI relies on fire protection and life safety systems in its facilities to provide protection of life and property and to ensure the continuity of important missions established by the Smithsonian. In order to sustain this level of protection, all fire and life safety systems must be maintained to ensure high reliability through an effective inspection, testing, and preventive maintenance program.

3. Fire protection and life safety systems and equipment shall be inspected, tested, and maintained in compliance with the manufacturer's recommendations and the attached appendices.

 

B. CHAPTER-SPECIFIC ROLES AND RESPONSIBILITIES

1. Building Manager

a. The building manager shall ensure all required inspections, operational tests and preventative maintenance are performed in accordance with the requirements of this Chapter, and all records are distributed to the Safety Coordinator and the Office of Safety, Health and Environmental Management (OSHEM).

b. Ensure all fire protection and life safety systems protecting leased facilities receive the required inspections, operational tests and preventative maintenance in accordance with this Chapter, either through requirements in the lease agreement, or through contracts under SI control.

2. Safety Coordinator

a. Verify that all required inspections, operational tests, and preventive maintenance are performed and all records are up to date, in accordance with the ITM requirements of this Chapter, through periodic facility inspections and document review.

b. Advocate prompt repair of fire protection and life safety systems and equipment by tracking deficiencies and ensuring required actions are completed in a timely manner.

3. Office of Facilities Management and Reliability (OFMR)

a. Upon notification of a fire protection/life safety system deficiency, the building manager shall ensure that repairs are made promptly in order to restore the system to proper working order.

b. The building manager shall retain ITM records for the facility's fire protection and life safety equipment per the requirements of this Chapter.

c. Perform the required inspections, testing and maintenance at specified intervals per the requirements of this Chapter, for all fire protection and life safety systems and equipment under their responsibility.

d. Ensure all fire protection system alterations and additions are properly documented.

e. Coordinate all ITM work performed with facility personnel, including scheduling and system impairment.

f. Collect and retain ITM information, reports, checklists, and other required records developed during the performance of ITM work.

g. Maintain a work order program to prioritize, initiate and track the repair or replacement of all malfunctioning fire protection and life safety system components to ensure systems are promptly restored to proper working order in a timely manner.

h. Distribute ITM information including schedules, inspection reports and deficiencies to the appropriate facility manager, Safety Coordinator and OSHEM. ITM records shall be distributed within thirty days of the last recorded ITM activity for that period.

i. Annually review ITM records and produce a report per the requirements of this Chapter.

4. Office of Protection Services (OPS)

a. Visually inspect portable fire extinguishers each month for proper mounting and charge per Attachment 15 of this Chapter. Initial and date the inspection tag and report missing, undercharged, or defective extinguishers to the building manager and Safety Coordinator.

b. Inspect emergency exit doors weekly per Attachment 12 of this Chapter to ensure proper operation in the event of an emergency. Immediately notify the building manager and Safety Coordinator of problems that could hinder egress and ensure they receive the required inspection reports.

5. Smithsonian Business Ventures, FONZ, and other SI Business Operations

a. Provide inspection, testing, and maintenance for all kitchen exhaust ducts and hoods, and kitchen fire suppression systems, per the requirements of this Chapter. Submit all records to the building manager and Safety Coordinator within two weeks of the ITM function performed.

b. Immediately notify the facility Safety Coordinator of any malfunction or code violation related to fire equipment within their space or affecting their operations.

c. Cease cooking operations while kitchen fire suppression systems are impaired, and ensure the impairment process has been initiated per Chapter 36, "Fire Protection", of this Manual.

d. Upon notification of a fire protection/life safety system deficiency, ensure repairs are made promptly in order to restore the system to proper working order.

 

C. PROGRAM COMPONENTS

1.TrainingITM tasks shall be performed by personnel trained/qualified in the maintenance and repair of the subject fire protection system or equipment. These personnel shall have available the manufacturer's service installation Manuals, maintenance Manuals, and service bulletins for the system or equipment being installed.

2. Impairments. All planned impairments of fire protection or life safety systems must be conducted in accordance with the precautions outlined in the Chapter 36, "Fire Protection", of this Manual.

3. Required Inspections, Testing and Maintenance. All fire protection/life safety systems and equipment shall be inspected, tested, and maintained in accordance with the requirements outlined in Attachments 1-17 of this Chapter.

 

D. RECORDS AND REPORTS. Two types of records are essential for the long term care of fire protection/life safety systems and equipment: the original records and periodic inspection, testing, and maintenance documentation.

1. Original Records. As of October 2007, original records of exiting fire protection / life safety systems where available and for all new systems shall be retained for the life of the system. OFMR shall also retain a copy of original records. Original records consist of the following:

a. Date of installation;

b. As-built drawings;

c. Operation and maintenance manuals;

d. Installer information (business address and telephone number);

e. Designation of equipment types and inventory of devices;

f. Equipment and system settings;

g. Equipment data sheets

2. ITM Documentation. Inspection, Testing, and Maintenance (ITM) documentation shall be retained for a minimum of 10 years for items that require annual or less frequent ITM. ITM documentation for items with frequencies greater than 1 year shall be retained for the life of the system. This documentation shall be retained by the facility manager. In addition, the OFMR units(s) responsible for ITM shall retain ITM records for all systems under its care. These records shall include all of the following information:

a. Date;

b. Procedure performed;

c. Name and signature of the servicing personnel and the organization's name that performed the work;

d. Test results;

e. Equipment and system deficiencies

f. Corrective actions, including parts replaced and settings or programming changes

3. Information Management System. OFMR shall establish and maintain an information management system for ITM documentation of all fire alarm, detection, suppression, smoke control and fire smoke damper and equipment under their care. The system shall provide the following:

a. An electronic database with retrievable historical records for each piece of equipment, group of similar pieces of equipment, or system;

b. Schedules for the scope and frequency of inspection and service for all equipment;

c. A method of persistent follow-up to ensure that inspection, testing, and maintenance services are being performed according to schedule;

d. A method of assigning priorities to equipment repair and maintenance tasks;

e. Specifications for special replacement parts and materials. A list of qualified suppliers for these items should be available by cross-reference;

4. ITM Report(fire alarm, detection, suppression, smoke control and fire smoke damper)

a. OFMR shall annually review the ITM data collected for facilities and generate a report which examines trends (e.g. failure rates, system aging) and identifies specific problems. The report shall include recommendations for improving system reliability and ITM efficiency, as well as resolving building coordination issues. The report shall also examine how the previous year's recommendations were addressed.

b. The report shall be submitted to the directors of the Office of Facilities Engineering and Operations (OFEO) and OSHEM within 30 days of the end of the year.

 

E. REFERENCES. National Fire Protection Association http://www.nfpa.org/

1. NFPA 10: Standard for Portable Fire Extinguishers

2. NFPA 12A: Standard on Halon 1301 Fire Extinguishing Systems

3. NFPA 13: Standard for the Installation of Sprinkler Systems

4. NFPA 14: Standard for the Installation of Standpipe and Hose Systems

5. NFPA 15: Standard for Water Spray Fixed Systems for Fire Protection

6. NFPA 17: Standard for Dry Chemical Extinguishing Systems

7. NFPA 17A: Standard for Wet Chemical Extinguishing Systems

8. NFPA 20: Standard for the Installation of Centrifugal Fire Pumps

9. NFPA 22: Water Tanks for Private Fire Protection

10. NFPA 24: Installation of Private Fire Service Mains and Their Appurtenances

11. NFPA 25: Standard for the Inspection, Testing and Maintenance of Water Based Fire Protection Systems

12. NFPA 33: Standard for Spray Application Using Flammable or Combustible Materials

13. NFPA 72: National Fire Alarm Code

14. NFPA 80: Standard for Fire Doors and Other Opening Protectives

15. NFPA 90A: Standard for the Installation of Air-Conditioning and Ventilating Systems

16. NFPA 92A: Standard for Smoke-Control Systems Utilizing Barriers and Pressure Differences

17. NFPA 96: Standard for Ventilation Control and Fire Protection of Commercial Cooking Operations

18. NFPA 101: Life Safety Code

19. NFPA 110: Standard for Emergency and Standby Power Systems

20. NFPA 780: Standard for the Installation of Lightning Protection Systems

21. NFPA 1962: Standard for the Inspection, Care, and Use of Fire Hose, Couplings, and Nozzles and the Service Testing of Fire Hose

22. NFPA 2001: Standard on Clean Agent Fire Extinguishing Systems